|
ACFM
Civil
Engineering Applications
| |
Introduction
Many
civil engineering structures contain or comprise steel frameworks,
welded together and painted or galvanized to prevent corrosion,
or coated with materials with specific properties, such as
intumescent paint for fire control. These are ideal for inspection
by ACFM due to its ability to work through coatings.
Many
contemporary building designs use exposed steelwork with high
quality, decorative and expensive coatings.
Other
typical structures that are routinely inspected with ACFM
include cranes, road and rail bridges, theme park rides and
roadside lighting. |
Overview
TSC
are widely involved in the ACFM inspection of steel constructed
buildings, whether in the temporary steelwork phase, lifting or
strand-jacking operations, substructures, superstructures or fascia
and aesthetic steelwork. In all these areas, ACFM is used to detect
inherent or fatigue related cracks, either on the bare steel or
through primer or high quality, expensive cosmetic finishes. This
rapid, non intrusive operation has saved clients many thousands
of pounds and time in categorizing potential or existing defects.
Inspection
of this kind is normally carried out against National
Structural Steelwork Specification for Building Construction, Issue
4, Annex C specifications.
Bridge
inspection is another expanding area for ACFM. Road bridges, rail
bridges, footbridges and historic bridges are all part of TSC's
expertise. From the inspection of mounts, swivels, supports and
bearers in the construction phase, through in-service fatigue cracking
through paint coatings or corrosion, to historic cast iron bridges
under protection or conservation orders – all can be assessed quickly
and efficiently with ACFM.
No
damage, no coating removal, minimum cleaning and an instant, permanent
electronic record.
Crane
inspection is complex because of the geometries involved, their
location, height and the fact that the majority are coated with
anti-corrosion paint. All of these factors mean that normal inspection
techniques are very difficult to apply. In the absence of a suitable
inspection technique, some cranes are removed from service because
of their age without knowing the complete condition of the crane.
Inspection and confirmation of their structural integrity would
elongate their useful life. When conventional inspection is required,
a crane can be out of service for a number of weeks while the coating
is removed for magnetic particle inspection and then reapplied.
TSC have extensive experience of dock cranes, tower cranes and container
cranes.
The
ability to use ACFM with rope access technicians allows inspection
in areas of difficult access without the need for scaffolding or
other support structure. In addition out-of-service time is reduced
as the use of ACFM eliminates the need to remove and reapply paint
or other protective coatings.
Projects
and Applications
Motorway
road bridges
 |
Project |
Equipment |
| Motorway bridge - box
girder inspection |
U19
AMIGO instrument
40mm 8 channel flat
array probe 5KHz
Standard weld probe
5KHz
Encoder weld probe
5KHz |
| |
ACFM inspection
was carried out on numerous cross braces on box girder bridge
structures on Bescot Viaduct. All inspection was confined
space entry, making ACFM an ideal method of inspection.
The scope of the
inspection was to provide an engineer, probe operator and
equipment to carry out ACFM testing on longitudinal box girder
welds at Bescot Viaduct.
Bescot Viaduct is
located at Junction 9 on the M6. The structures to be inspected
were chosen by the client prior to the inspection.
The purpose of the
work was to detect any surface breaking defects (horizontal
or vertical) in the weld cap or vicinity of the selected weld
and toes. |
Civil
engineering
 |
Project |
Equipment |
| Pre-lift qualification
of temporary steelworks |
U19
AMIGO instrument
Standard weld probe
5KHz
Straight long nose
probe 5KHz
Right angle mini
probe 5KHz
Straight mini probe
5KHz
40mm 8 channel flat
array probe 5KHz |
| |
TSC
Inspection Systems worked closely with Watson Steel, the manufacturers
of temporary and permanent steelworks at London Heathrow Airport
Terminal 5 constructions.
Work began to raise the roof in April
2004 when the first of six 2,500 tonne steel sections was
lifted. Each 117m arch section was assembled at ground level
and the roofing components fitted before being jacked up approximately
40m to their final position.
Assembling the roof
at a low level reduced the risks of working at height, and
allowed cranes to operate inside the radar zone imposed on
the construction team by the airport operations.
The use
of TSC's ACFM inspection techniques was effective in quickly
and accurately assessing the integrity of the welded temporary
steelwork of the jacking beams, through the paintwork, before
the first lifts took place.
ACFM inspection was also carried out extensively on the substructure
steelwork and critical components on the airside bridges.
All ACFM inspection at T5 was
carried out through coatings, whether primer or final intumescent
paint, which is extremely difficult to remove. Inspection
was far faster than conventional methods, enabling construction
to carry on without major delay. |
River
bridges
 |
Project |
Equipment |
| Motorway bridge - plate
inspection |
U19
AMIGO instrument
40mm 8 channel flat
array probe 5KHz
Standard weld probe
5KHz
Encoder weld probe
5KHz |
| |
Bray
Bridge was constructed in 1961 and carries the M4 over the
River Thames at Maidenhead.
ACFM was used in conjunction with Magnetic
Particle Inspection (MPI) to check specified welds for defects.
All inspection was carried out through the existing paint
coating, greatly reducing the amount of inspection time and
enabling engineers to have an accurate, permanent record of
results that can be used for condition monitoring over a long
period.
ACFM inspection was carried out primarily with a single coil
standard weld probe as this was most suited to the geometry
of the welds to be inspected. A flat 8 channel array probe was
used in areas where wider coverage was required (40mm wide strips),
and a 3 channel encoder weld probe used on welds where access
permitted. The latter gave the advantage of covering an area
deeper into the HAZ (Heat Affected Zone) and observe the coil
response if a defect was found. A further benefit of using this
probe is the position encoding, allowing the pinpointing of
defect ends from the start of the scan. |
Civil
engineering
 |
Project |
Equipment |
| Civil engineering site-works |
U19
AMIGO instrument
40mm 8 channel flat
array probe 5KHz
Standard weld probe
5KHz)
Right angle pencil
probe 5KHz
Straight mini pencil
probe 5KHz |
| |
TSC
were contracted to carry out ACFM inspection on numerous louvre
support column assemblies, louvre roof support columns and
base supports at Chiswick Park, London.
The
purpose of the inspection was to locate any surface breaking
defects in the weld caps and weld toes, through the existing
paint coating. All butt welds were ground flat and painted
to finished standard. An ACFM array probe with width coverage
of 40mm was used, one pass either side of the weld centre
line to provide total width coverage of approximately 80mm
through the full circumference of the weld. Single coil weld
probes were used on the base plate fillet welds on the louvre
roof support columns and on the circumferential welds on the
base stub columns.
Use
of the array probe provided simultaneous data for both X and
Y directions (i.e. longitudinal and transverse to the line
of the weld). |
Railway
Bridge Inspection
 |
Project |
Equipment |
| Railway bridge - box
gider inspection |
U19
AMIGO instrument
40mm 8 channel flat
array probe 5KHz |
| |
Hyde
Lane underbridge was constructed in 1969 and carries the two
lines of the Bristol and Gloucester line over Hyde Lane one
mile south west of the A435 in Cheltenham. It is an early
form of the ‘Western Region Box Girder' bridge, constructed
from three main box girders, cross girders, deck plate and
ballasted track. The superstructure is supported on reinforced
concrete cill beams on masonry stone abutments and wing walls.
ACFM
was carried out using a flat 40mm array probe to investigate
the integrity of corners on cross girder webs. Inspection of the up line side
was completed in one night shift, with the benefit of only
having a partial road closure for 12 hours. The down line
side was again completed in a second 12 hour shift. |
Historic
Bridge Inspection
 |
Project |
Equipment |
| Historic bridge inspection
- dissimilar metals |
U19
AMIGO instrument
40mm 8 channel flat
array probe 5KHz
Micro pencil probe
5khz |
| |
Another
challenging project TSC has been involved in is the inspection
of welds on an historic bridge, constructed in 1867, spanning
the river Thames.
Longitudinal
beam web repairs had been carried out on the bridge, involving
joining the original cast iron material with steel insert
plates. Time and weather over many years had caused corrosion
and degradation of some of the side panels.
Tests
carried out in TSC's workshop on material samples prior to
the inspection resulted in a high degree of confidence in
the system for use on what is an unusual combination of welded
materials, and the fact that there was a relatively thick
primer and paint coating.
ACFM
inspection was carried out using a hand held array probe with
positioning encoder. The advantage of using the array system
over single coil probes is that a much larger area can be
inspected in one pass of the probe. This situation was ideal
as the welds had been ground flat. In practice, an area of
approximately 35mm wide was covered, thus inspection of the
entire weld face and heat affected zone was accomplished in
a single pass with the paint coating completely untouched.
|
Railway
Bridge Inspection
 |
Project |
Equipment |
| Rail
underbridge
|
U19
AMIGO instrument
Standard weld probe
5KHz
Straight pencil probe 5 KHz
|
| |
Several major UK
based civil engineering contractors were working
in partnership on the repair and maintenance of a pair of
steel underbridges, just to the north of
Oxford Station. The bridges each carry two tracks over a waterway
in a single span. The bridge has recently had a new abutment
built under the southern end to give it proper support.
The six main girders have between
them span cross girders which in turn support rail bearers
and the deck plate. A limited amount of ACFM testing was carried
out to assess if any fatigue cracking was present. |
Queen
Elizabeth Bridge
 |
Project |
Equipment |
| Roadside
lamp post weld inspection |
U19
AMIGO instrument
Standard weld probe 5KHz |
| |
ACFM
inspection was conducted on 114 QEII bridge lamp post welds. No cleaning or paint removal was
required. Inspection was carried out by rope access technicians
and a remote ACFM operator, removing the need for plant, cherry
pickers or scaffold. |
Crack
Detection
/ Applications
/ Civil Engineering 1
2 3 4
5 6
7 8
9 10
Next
|